Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Which of the following pieces portrays the female form with a blend of Renaissance idealization and mannerist stylization? A. Allegory with Venus and C
How did the north american colonies achieve the remarkable population growth of the 18th century?
In what geographic region were Islam, Judaism, and Christianity founded
What major problems or conditions led to the rise of totalitarian leaders?
people who in exchange for their military service, held land for a king or lord a.telling b.thanes
If a ploynominal has four terms 3x^3+5x+6x^2+10 which factoring method can be considered
What it called when daughter cells get an exact copy of dna from the parent cell
.......,.........,........
There is a sales tax of $14 on an item that costs $147before tax. A second item costs$84 before tax. What is the sales tax on the second item?
You complete weekly practice tests for three months before you are scheduled to take the lsat. which method are you using to manage stress?