If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

ASAP WILL GIVE BRAINLIEST
What was Cardinal Richelieu's longest lasting legacy?
The moon's distance from Earth varies in a periodic way that can be modeled by a trigonometric function. When the moon is at its perigee (closest point to Earth
the length of a room is 10.5 feet what is the length of the room in inches.
what was the result of the efforts of the civil right movements
Examine the diagram and information to answer the question.A circle in the coordinate plane has a radius of 5 and a center at point (5,4).Point (x,y) lies on th
What is the difference between a free enterprise economy and a socialist economy? A. In a socialist economy, there are no government regulations. B. In a so
how did environmental factors impact trade routes
What is the solution to the system ofs below?​
How do ethnicity and nationality differ?