MaThWiZz6123 MaThWiZz6123
  • 02-07-2021
  • Mathematics
contestada

It take 4 people 40 minutes to clean a garden. How long will it take 6 people to clean the same garden

Respuesta :

loconte loconte
  • 02-07-2021

Answer:

4/9 of an hour (26.666 minutes)

Step-by-step explanation:

4 * x * 40/60 = 1

x * 160/60 = 1

x=60/160 = 6/16 = 3/8 (this is the rate for one worker)

~~~~~~~~~~~~~~~~

6 * (3/8) * x = 1

x = 4/9

Answer Link

Otras preguntas

Use the formula d= to find the value of the missing variable. r=8 ​mph, t =6 hours
How did Ford deal with Nixon during his own presidency?
In contrast to sixty percent of kindergarteners having good cognitive skills that make them more likely to succeed, how many have the necessary social skills to
Solve 3x + 4 = 12(x + 2) - 5x. Justify each step.
What was considered to be the first keyboard instrument? hydraulis kithara panpipes aulos
(sinx+cosx)2=sin2x+1​
How do you say "I HATE MYSELF" in French
In a two candidate election, Amanda received 7 times as many votes as Joshua. If a total of 16 votes were cast, then how many votes did Joshua receive?
Help me fill in the blanks please!
Describe how to estimate a non-perfect square root to the hundredths place without using a calculator.