PLEEASE ANWER QUICK: The project manager is writing the requirements document. Which phase of the project life cycle is he in?
project closure
project planning
project initiation
project execution ​

Respuesta :

Animmango
Animmango Animmango
  • 01-05-2021

Answer:

I think, project execution. He is writing the requirements document. which mean it doesn't project closure and initiation. then he did it which mean it doesn't project planning.

Answer Link

Otras preguntas

1. Mes grands-parents habitent à la campagne en Normandie. Au printemps pendant les vacances je vais avec mon frère Jean et ma soeur Lou chez mes grands-parents
what battle stopped the spread of Islam into Europe
How should succesful businesses respond in a crisis? How does this information relate to our own lives when facing a personal crisis? Give a total of 5 reasons.
1 Identify whether the series summation of 16 open parentheses 5 close parentheses to the I minus 1 power from 1 to infinity is a convergent or divergent geomet
A light bulb manufacturer randomly tests 1500 bulbs and finds that 2 are defective. How many defective bulbs would be expected in a shipment of 24,000 bulbs?
If 27% of a number is 11.34, what is the number?
once stimuli are in the brain they are processed by
what role did korea have in the development of east asia
A pair of shoes cost £54 in a 40% off sale. Find the original price of the shoes.
describe the three system related to the skeletal system