When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

Graph the circle which is centered at -5,1 and has a radius of 4 units
how many how many ministers in India​
On June ​1, 2018​, Perfect Performance Cell Phones sold $ 17,000 of merchandise to Ashton Trucking Company on account. Ashton fell on hard times and on July 15
Anyone, please help me answer this question.
What is the quotient of 56,700 ÷ 15?
Why did the ancient Greeks depend on the sea for much of their food? A. The mountainous terrain of Greece limited the amount of farmland. B. The Greek peninsu
Which amendment guarantees you a jury trial in a criminal case? 6th 8th 7th 9th
Someone please help me with this! Is this a independent or dependent? Explain why.
A basic concept in economics is that al resources are?
5/10 as a unit fraction