Estimate the quantity of soil to be excavated from the borrow pit​

Respuesta :

lola2487
lola2487 lola2487
  • 04-08-2019

Answer

1056

Explanation:

for example

A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

Quantity of soil to be excavated from pit in m3

Answer Link

Otras preguntas

Analyzing Ancient Greek culture
Please explain how to do unit conversion, for example a rectangle has a width of 12cm and a length of 5cm and you're solving for the area obviously, it would be
Need help ASAP!!!!!!!
(07.02 LC) What was the primary religion of slaves in the Southern states? (5 points) Atheism Agnosticism Christianity Islam
Choose the coordinate pairs that are NOT shown on the graph. (3, 2) (−6, 3) (1, −1) (−6, −4) (4, −2)
Write two short paragraphs in Spanish about an illness or an injury that you suffered in the past. Include information about how it happened and how it was trea
(ASAP PICTURE ADDED) What is the simplified form of the following expression?
What three elements of the peace treaties could be exploited by Hitler to build up fierce nationalism among the German people?
A(n) ______of the audio or video clip makes the content easily accessible to people with hearing disabilities.
1/2x+3/2(x+1)-1/4=5​