it takes 20 people 24 days to build a barn. in how many days will the barn be built if they had 32 people working

Respuesta :

bluevortexwitepower bluevortexwitepower
  • 02-02-2019

Answer:

15 days

Step-by-step explanation:

Number of ppl it takes to build a barn in 24 days=20

Time it will take 32 people to build the barn=24*20/32=15 days

Answer Link

Otras preguntas

Which was not part of Kennedy's New Frontier agenda?
Which of the following shows the graph of a line through (–2,2) and (2,4)?
4. Helene invested a total of $1000 in two simple-interest bank accounts. One account paid 5% annual interest; the other paid 6% annual interest. The total amou
Drag a statement or reason to each box to complete this proof. Given: segment M N is congruent to segment N L. Segment N L is congruent to segment J N. Segmen
model with mathematics.Orange taxi charges 2.75 as soon as you step in and 2.50 per mile.Write a function f (x) that describes the total cost of a ride of x mi
If Michel drove 273 miles in4 hour, what was her speed in miles per hour
The a0 manager is an application that displays what is currently happening on your computer. fill in the a0
4) The sum of two numbers is 21. The smaller number is three more than half the larger number. What are the two numbers? 13) You purchase 5 movies and a CD. The
Is it easy or hard to obtain the RDA through diet
Why did the British surrender to the Americans in the Battle of Yorktown in 1781?